Guangdong Electric Power Development Co.Ltd(000539) : Guangdong Electric Power Development Co.Ltd(000539) voluntary information disclosure announcement on the completion of power generation in 2021

Securities code: 000539, 200539 securities abbreviation: Guangdong Electric Power Development Co.Ltd(000539) , Guangdong electric power B Announcement No.: 2022-08

Corporate bond Code: 149113 corporate bond abbreviation: 20 Yuedian 01

Corporate bond Code: 149369 corporate bond abbreviation: 21 Yuedian 01

Corporate bond Code: 149418 corporate bond abbreviation: 21 Yuedian 02

Corporate bond Code: 149711 corporate bond abbreviation: 21 Yuedian 03

Guangdong Electric Power Development Co.Ltd(000539)

On the completion of power generation in 2021

Voluntary information disclosure announcement

The company and all members of the board of directors guarantee that the information disclosed is true, accurate and complete without false records, misleading statements or major omissions.

1、 Completion of power generation in 2021

According to the company’s statistics, in 2021, the company completed 119.869 billion kwh of power generation according to the consolidated statement, with a year-on-year increase of 62.53%; Among them, 99.983 billion kwh of coal power was completed, with a year-on-year increase of 66.46%, 16.96 billion kwh of gas power, with a year-on-year increase of 42.21%, 1.793 billion kwh of wind power, with a year-on-year increase of 40.19%, 344 million kwh of hydropower, with a year-on-year decrease of 28.42%, and 789 million kwh of biomass power generation. The cumulative on grid power according to the consolidated statement was 113.285 billion kwh, an increase of 62.16% year-on-year. The annual power generation data of each power plant of the company in 2021 are as follows:

Power generation on Grid

Type company name / project name (100 million kwh) (100 million kwh)

Year on year 2021 year on year 2021

(%) (%)

Shajiao A power plant 40.61 19.05 37.96 19.29

Guangdong Huizhou Pinghai Power Plant Co., Ltd. 125.81 30.57 120.13 30.61

Guangdong honghaiwan Power Generation Co., Ltd. 137.10 28.51 129.29 28.65

Guangdong Yuedian Jinghai Power Generation Co., Ltd. 176.91 26.69 167.42 26.70

Coal power Zhanjiang Electric Power Co., Ltd. 59.32 28.56 55.36 28.87

Guangdong energy Maoming Thermal Power Plant Co., Ltd. 55.17 26.83 51.17 27.46

Guangdong Yuedian Dapu Power Generation Co., Ltd. 66.89 45.29 63.19 46.15

Guangdong Shaoguan Yuejiang Power Generation Co., Ltd. 82.33 64.51 76.71 65.40

Zhanjiang Zhongyue Energy Co., Ltd. 54.47 55.32 50.73 55.33

Guangdong Yuedian Bohe Energy Co., Ltd. 75.02 – 71.16-

Guangdong Shajiao (Plant C) Power Generation Co., Ltd. 91.63 – 83.72-

Guangdong Yuedian Yunhe Power Generation Co., Ltd. 30.66 – 28.43-

Tumushuk Thermal Power Co., Ltd. 3.91 – 3.64-

Shenzhen Guangqian Electric Power Co., Ltd. 37.09 -9.88 36.40 -9.46

Gas power Guangdong Huizhou natural gas power generation Co., Ltd. 77.50 -0.77 76.03 -0.84

Guangdong Yuehua Power Generation Co., Ltd. 25.96 – 25.45-

Guangdong Yuedian Xinhui Power Generation Co., Ltd. 29.05 – 28.39-

Guangdong Wind Power Co., Ltd. 7.87 202.64 7.55 201.46

Wind power Guangdong Yuedian Leizhou Wind Power Co., Ltd. 0.84 -7.46 0.74 -14.82 Guangdong Yuedian Zhanjiang Wind Power Co., Ltd. 1.72 -9.61 1.62 -9.19

Guangdong Yuedian qujie Wind Power Generation Co., Ltd. 7.50 1.52 7.13 0.23

Hydropower Lincang Yuedian Energy Co., Ltd. 3.44 -28.42 3.39 -28.13

Biomass Guangdong Yuedian Zhanjiang Biomass Power Generation Co., Ltd. 7.89 – 7.25-

Note 1: phase I project of Bohe power plant constructed by Guangdong Yuedian Bohe Coal Power Co., Ltd. (2) × 1000MW) was officially completed and put into operation in November 2020. It is not applicable to calculate the year-on-year changes of power generation and on grid power in 2021.

Note 2: the company acquired the equity of Guangdong Shajiao (Plant C) Power Generation Co., Ltd., Guangdong Yuedian Yunhe Power Generation Co., Ltd., Guangdong Yuehua Power Generation Co., Ltd. and other companies in 2021, which belongs to the business merger under the same control. The power generation and on grid power of the above enterprises and their subsidiaries are counted according to the annual caliber; In 2021, the company increased its capital to hold Tumushuke Thermal Power Co., Ltd., which is a business merger not under the same control. Its power generation and on grid power are counted from the date when they are included in the scope of the consolidated statements.

2、 Installed capacity by 2021

By the end of 2021, the company had a controllable installed capacity of 29.9426 million KW, of which the holding installed capacity was 28.2292 million kW (including the newly increased holding installed capacity of 6.6172 million kW in 2021) and the equity participation installed capacity was 1.7134 million KW. Among them, the installed capacity of coal-fired power generation holdings is 20.55 million KW, accounting for 72.8%; The installed capacity of gas power holding is 5.472 million KW, accounting for 19.4%; The holding installed capacity of wind power, hydropower, biomass and other renewable energy power generation is 2.2072 million KW, accounting for 7.8%.

In addition, the company’s entrusted installed capacity is 8.854 million kW (6.65 million kw of thermal power and 2.204 million kw of hydropower), and the above controllable installed capacity and entrusted installed capacity are 38.7966 million kW in total.

It is hereby announced.

Guangdong Electric Power Development Co.Ltd(000539) board of directors January 26, 2002