Guangdong No.2 Hydropower Engineering Company Ltd(002060) : Announcement on winning the bid for the general contracting of design and construction of the new project of Yangchun avenue to Yangchun east station section of Guangzhou Zhanjiang high speed railway on Provincial Highway s539

Securities code: 002060 securities abbreviation: Guangdong No.2 Hydropower Engineering Company Ltd(002060) Announcement No.: pro 2021-088

Guangdong No.2 Hydropower Engineering Company Ltd(002060)

About provincial highway s539 Yangchun Avenue Guangzhou Zhanjiang high speed railway

Announcement of winning the bid for general contracting of design and construction of Yangchun east station section new project the company and all members of the board of directors guarantee that the information disclosed is true, accurate and complete without false records, misleading statements or major omissions.

On December 22, 2021, Guangdong No.2 Hydropower Engineering Company Ltd(002060) (hereinafter referred to as “the company”) received the letter of acceptance (No.: gzjz [2021] No. [07309]) from Guangzhou public resources trading center. The relevant contents are announced as follows:

The letter of acceptance determines that the consortium composed of the company and Guangdong transportation planning, design and Research Institute Group Co., Ltd. (hereinafter referred to as “Guangdong transportation design institute”) (the company is the leader of the consortium and Guangdong transportation design institute is the member of the consortium) is “general contracting for design and construction of new project from Yangchun avenue of provincial highway s539 to Yangchun east station section of Guangzhou Zhanjiang high speed railway” The successful bidder. The contracting content is the contracting content specified in the bidding documents, and the total bid winning price is 5893817400 yuan, of which the bid winning price of the company’s engineering cost is 5786461880 yuan.

According to the bidding documents, the project starts at the intersection of chunzhou Avenue and Yangchun Avenue, with the starting point chainage of K92 + 613. From west to East, the line passes through Shilan reservoir, dengxintang and xuetanggang, and ends at Yangchun east station, the terminal chainage of k103 + 170. The total length of the line is 10.557 km. It is proposed to adopt asphalt concrete pavement, with 4 major bridges, 3 medium bridges and 33 culverts, 9 grade level crossings. K92+613~K95+613

Securities code: 002060 securities abbreviation: Guangdong No.2 Hydropower Engineering Company Ltd(002060) Announcement No.: pro 2021-088

The section is constructed as class I Highway and urban road standard, with a length of 3km, two-way six lane, subgrade width of 45m and design driving speed of 60km / h; K95 + 613 ~ k103 + 170 section adopts the standard of class I highway, with a length of 7.557km, two-way six lane, subgrade width of 35m and design driving speed of 80km / h. The whole line includes highway engineering and municipal engineering, including road subgrade, pavement engineering, drainage engineering, culvert engineering, street lamp engineering, traffic engineering, greening engineering, etc.

According to the Consortium Agreement, the company undertakes the professional construction works of the project; Guangdong communications design institute undertakes the professional engineering of survey and design of the project.

The formal contract of the project has not been signed, and the contract terms are still uncertain. The company will timely perform the obligation of information disclosure according to the follow-up progress. Please pay attention to the investment risk.

It is hereby announced.

Guangdong No.2 Hydropower Engineering Company Ltd(002060) board of directors December 23, 2021

 