Securities code: 000151 securities abbreviation: China National Complete Plant Import And Export Co.Ltd(000151) Announcement No.: 2021-89
The company and all members of the board of directors guarantee that the information disclosed is true, accurate and complete without false records, misleading statements or major omissions.
China National Complete Plant Import And Export Co.Ltd(000151) about
Announcement on participating in the bidding of Cixi construction waste resource disposal center project
On December 22, 2021, China National Complete Plant Import And Export Co.Ltd(000151) (hereinafter referred to as “the company”) held the 23rd Meeting of the 8th board of directors, deliberated and adopted the proposal on the proposal to participate in the bidding of Cixi construction waste recycling disposal center project , we agree that the company will participate in the bidding of Cixi construction waste resource disposal center project, and authorize the company’s management to handle matters related to this bidding. The relevant information is hereby announced as follows:
1、 Main information of bidding project
1. Construction site: the project is located in the west of banjuepu, Xinpu Town, Cixi City;
2. Construction scale: the land area is 55606 square meters, with an annual treatment of 100000 tons of ordinary construction waste, 630000 tons of decoration waste (including large waste) and 700000 m3 (800000 tons) of waste mud; 3. Total investment of the project: 54017700 yuan (including interest during construction);
4. Amount and proportion of capital contribution: the capital of the project accounts for 20% of the total investment of the project, and the paid in shall be paid according to 20% of the total investment of the bid winning price, of which the social capital party accounts for 66.5% of the total capital of the project; The government’s investment representatives account for 33.5% of the total capital of the project, and both parties contribute in currency.
5. Cooperation mode and duration: the project adopts the operation mode of construction operation handover;
The cooperation period is 27 years, including 2 years of construction and 25 years of operation.
2、 Impact of this bid on Listed Companies
Since the first half of 2021, the company has continuously followed up the project of Cixi construction waste resource disposal center. The company’s bidding is to implement the company’s “14th five year plan”. If the bid is won, it will be conducive to expanding the municipal solid waste business. There is still uncertainty about whether the project can win the bid, and the company will perform the obligation of information disclosure according to the follow-up progress.
3、 Documents for future reference
Resolution of the 23rd Meeting of the 8th board of directors of the company
China National Complete Plant Import And Export Co.Ltd(000151) board of directors December 23, 2001