Securities code: 002061 securities abbreviation: Zhejiang Communications Technology Co.Ltd(002061) Announcement No.: 2022-013 bond Code: 128107 bond abbreviation: Jiaoke convertible bond
Zhejiang Communications Technology Co.Ltd(002061)
Announcement on winning the bid
The company and all members of the board of directors guarantee that the information disclosed is true, accurate and complete without false records, misleading statements or major omissions.
Zhejiang Jiaogong Group Co., Ltd., a subsidiary of Zhejiang Communications Technology Co.Ltd(002061) (hereinafter referred to as "the company"), and its subsidiaries participated in the bidding for the general contracting of design and construction of section sjsg of Lanxi Majian Jiande daciyan section of national highway 351 and the PPP project of Jintang Dasha section of double track Yongzhou expressway. Recently, the company received the letter of acceptance of the project from Zhejiang Jiaotong Engineering Group Co., Ltd. and now announces the main contents as follows:
1、 Overview of the winning project
(I) project name: sjsg bid section of general contracting for design and construction of Majian Jiande daciyan section of Lanxi National Highway 351
Bid winning price: 2366119999.00 yuan
Tenderee: Lanxi City Investment Group Co., Ltd
Winning bidder: Zhejiang Jiaogong Hongtu Traffic Construction Co., Ltd. (leader), China Highway Engineering Consulting Group Co., Ltd. (member)
Construction period: the design construction period is 6 months (calculated from the signing of the general contract agreement for design and construction); Total construction period: 36 months (calculated from the time indicated in the commencement order issued by the supervisor).
Division of labor of the consortium: Zhejiang Jiaogong Hongtu Traffic Construction Co., Ltd., as the leader of the consortium, undertakes the construction completion of highway engineering, traffic engineering and facilities along the line within the bidding scope of the project, defect repair during the defect liability period and warranty during the warranty period; China Highway Engineering Consulting Group Co., Ltd. undertakes the survey and design of highway engineering, traffic engineering and facilities along the line within the bidding scope of the project, including location survey and detailed survey, construction drawing design, preparation of construction drawing budget, adjustment of construction drawing budget, preparation of bill of quantities, preparation of special technical specifications for construction projects, follow-up services (including dynamic design) Professional projects such as relevant scientific research (if necessary) and special reports (if necessary).
(2) Project Name: PPP project of Jintang Dasha section of double track Yongzhou Expressway
The total length of the expressway line of the project is about 18.92km (the implementation length of the main line is about 18.56km, including the length of three highway railway joint bridges of Xihoumen, Taoyaomen and fuqimen), 16 main line bridges of about 10336m (including the main line bridge in the interchange area and three highway railway joint bridges of 4519m), and the synchronous construction connecting line at the end of the line is about 0.63km.
Bid winning price: total investment of PPP project, total bid price 10754472192.00 yuan; The bid price of construction and installation engineering cost of land section is 267302300.00 yuan, and the average annual operation subsidy reported by social capital is 333700000.00 yuan
Cooperation period: 31 years (including 6 years of construction period and 25 years of operation period);
Tenderee: Zhoushan bridge construction management center;
Winning bidder: Zhejiang Communications Investment Group Co., Ltd., Zhejiang Jiaogong Group Co., Ltd., Zhejiang Gaoxin Technology Co., Ltd., Zhejiang Jiaogong road and Bridge Construction Co., Ltd., China Railway Bridge Bureau Group Co., Ltd., the Fifth Engineering Co., Ltd. of China Railway Bridge Bureau Group, China Railway Construction Corporation Limited(601186) Bridge Engineering Bureau Group Co., Ltd. Zhejiang Jiaogong Group Co., Ltd. and Zhejiang Jiaogong road and Bridge Construction Co., Ltd. are subordinate companies of the company; Zhejiang Communications Investment Group Co., Ltd. is the controlling shareholder of the company, and Zhejiang Gaoxin Technology Co., Ltd. is the controlling subsidiary of the controlling shareholder. The above two companies are related parties of the company;
The proportion of internal contribution of social capital is tentatively determined as follows: Zhejiang Communications Investment Group Co., Ltd. holds 44.409%, Zhejiang Jiaogong Group Co., Ltd. holds 0.750%, Zhejiang Gaoxin Technology Co., Ltd. holds 0.200%, Zhejiang Jiaogong road and Bridge Construction Co., Ltd. holds 0.050%, and China Railway Bridge Bureau Group Co., Ltd. holds 37.957%, The Fifth Engineering Co., Ltd. of China Railway Bridge Engineering Bureau Group holds 0.100% of the shares, and China Railway Construction Corporation Limited(601186) Bridge Engineering Bureau Group Co., Ltd. holds 16.534% of the shares;
Division of labor among members of the consortium: Zhejiang Communications Investment Group Co., Ltd. is the leader of the consortium, Zhejiang Jiaogong Group Co., Ltd., Zhejiang Gaoxin Technology Co., Ltd., Zhejiang Jiaogong road and Bridge Construction Co., Ltd., China Railway Bridge Bureau Group Co., Ltd., the Fifth Engineering Co., Ltd. of China Railway Bridge Bureau Group China Railway Construction Corporation Limited(601186) Bridge Engineering Bureau Group Co., Ltd. is a member of the consortium. The leader of the consortium, Zhejiang Communications Investment Group Co., Ltd., is responsible for the registration of the project company and contributes to the project company according to the agreed time and proportion; As the leader, take the lead in organizing, managing, assisting and supervising the financing, construction, operation and handover of the project company (investment, financing, operation and handover). The consortium members Zhejiang Jiaogong Group Co., Ltd., Zhejiang Gaoxin Technology Co., Ltd. and China Railway Bridge Bureau Group Co., Ltd. cooperate with the leader to handle the registration of the project company and contribute to the project company according to the agreed time and proportion; Cooperate with the leader to associate, assist and supervise the project company to complete various performance behaviors (investment and financing) such as financing, construction, operation and handover. The consortium members Zhejiang Jiaogong road and Bridge Construction Co., Ltd., the Fifth Engineering Co., Ltd. of China Railway Bridge Engineering Bureau Group and China Railway Construction Corporation Limited(601186) Bridge Engineering Bureau Group Co., Ltd. cooperate with the leader to handle the registration of the project company and contribute to the project company at the agreed time and proportion; Cooperate with the leader to associate, assist and supervise the project company to complete various performance behaviors such as financing, construction, operation and handover; Take charge of the project construction (investment, financing and construction) together with other consortium members participating in the construction.
2、 Impact on Listed Companies
The double track of Yongzhou expressway is an important part of the skeleton road network of "three horizontal and one vertical" in the layout of Zhoushan expressway network. It is also an important part of the Shanghai Zhouzhou Ningbo sea crossing channel in the outline of the regional integration development plan of the Yangtze River Delta. It plays an important role in alleviating the traffic pressure of Jintang Shuangqiao section of Yongzhou expressway.
The winning project conforms to the strategic layout of the company's main business and can consolidate the company's market competitiveness and market share in the Yangtze River Delta. If the above winning project is successfully implemented, it will have a positive impact on the company's future performance. 3、 Risk tips
1. The investment agreement and construction agreement of PPP project of Jintang Dasha section of double track Yongzhou expressway have not been signed; The construction contract of the bid winning project of section sjsg of general contracting for design and construction of Majian Jiande daciyan section of Lanxi National Highway 351 has not been signed; The terms of the contract are still uncertain, and the performance of the contract shall be subject to the terms finally signed;
2. The company will sign a written contract with the tenderee as soon as possible and perform the obligation of information disclosure as required; 3. After the formal contract is signed, if the impact of unpredictable or force majeure factors is encountered in the performance process, it may lead to the risk that the contract cannot be fully performed or terminated. Please pay attention to investment risks.
It is hereby announced.
Zhejiang Communications Technology Co.Ltd(002061) board of directors February 22, 2022