The reporter of the financial Associated Press learned from the performance briefing of Jinyuan Ep Co.Ltd(000546) 2021 that the company's 8000 mistake project was affected by the epidemic and other factors. The project process was changed from "achieving the production capacity of 2000 tons / year in phase I by the end of May this year" to "striving to achieve the output of the first ton of products in May this year". However, the total production capacity of 8 Tcl Technology Group Corporation(000100) 00 tons completed by the end of this year remains unchanged, and the company is expected to reach full production in 2023. Xu Gang, chairman of the board, said that the planned output of lithium carbonate of the company in 2022 is 2000 tons.