At 20:00 on April 11, 5030 beds of Jinshan fangcang hospital, which was built and operated by Shanghai Construction Group Co.Ltd(600170) construction, operation and maintenance, were all completed. It took only 48 hours and ran out of the construction acceleration retrogradely. After receiving the urgent task on the morning of April 8, Shanghai Construction Group Co.Ltd(600170) responded quickly and set up the emergency reconstruction headquarters of the shelter hospital headed by Ye Weidong, deputy secretary of the Party committee and president. The fire line of Shanghai Construction Group Co.Ltd(600170) No. 4 construction group gathered and dispatched elite and brave generals. The first batch of builders led the field in the afternoon of that day. On April 9, the large-scale construction kicked off, and more than 2700 builders, regardless of difficulties and conditions, efficiently completed the construction of beds and internal structures.
Jinshan fangcang hospital is located in Tianhua Road, Jinshan District, with a total construction area of nearly 50000 square meters. After reconstruction, four factories will treat mild and asymptomatic patients with covid-19 pneumonia. It is planned to be delivered on April 14. After the official opening of the shelter hospital, Shanghai Construction Group Co.Ltd(600170) will also undertake the task of operation and maintenance support. Today, we have discussed the details of the follow-up task with the medical team, which is also the first time Shanghai Construction Group Co.Ltd(600170) will undertake the all-round operation and maintenance task of the shelter hospital.
Jinshan fangcang hospital takes 1.5 hours to drive from the downtown area of Shanghai. It was originally five factories. There were insufficient water and electricity, old and mottled walls and accumulation of garbage and sundries. Compared with large-scale sports exhibition facilities such as Minhang gymnasium and New International Expo Center, the overall construction foundation was poor and the construction was more difficult. The builders had no time to rectify when they entered the site on April 8 and could not pay attention to detailed planning, so they had to clean up the site and carry out construction at the same time, He robbed the working face that night.
In addition to the reconstruction of four workshops into a shelter hospital, there are also work accommodation, material warehouse, office area, command center and other areas.
At 20:00 p.m. on April 9, after trying to overcome the great difficulties in personnel and material allocation, 189 on-site managers and 1389 builders fully invested, and the large-scale construction officially kicked off. With efficient command and systematic management of the headquarters and scientific organization of the fourth construction group, the construction content is divided into four parts, which are in the charge of civil engineering units and municipal and installation professional units, and managed by districts and blocks. On the construction site, all links are coordinated, upstream and downstream are linked, the construction period is accurate to hours, the construction responsibility is assigned to people, accurate and efficient, day and night. In 24 hours, 55000 square meters of PVC floors were laid, 79 engineering vehicles were waiting, and 120 containers were hoisted. Within 48 hours, the construction of 5030 beds and internal structure were completed. As of the evening of April 11, there were more than 200 on-site managers and 2500 front-line builders.
With the full completion of 5030 beds, the following work will be carried out, such as air conditioning, fire protection, pipeline, electrical, communication, construction and transformation of road water pumps, so as to further improve the comprehensive treatment capacity of the shelter. The shelter hospital is planned to be completed and delivered on April 14.
On the basis of doing a good job in construction, after the official opening of Jinshan shelter hospital, Shanghai Construction Group Co.Ltd(600170) will also undertake the operation and maintenance support task of the whole shelter hospital, and provide security, cleaning, accommodation, catering, commuting, material procurement and management, facility and equipment operation and maintenance and other services for the shelter hospital. At present, Shanghai Construction Group Co.Ltd(600170) has established the operation and maintenance support headquarters of Jinshan shelter hospital.