After AI express, investors ask questions on the investor interaction platform: Hello, how long did it take for the company's phase I mining to reach production from the approval? Thank you.
Yongxing Special Materials Technology Co.Ltd(002756) ( Yongxing Special Materials Technology Co.Ltd(002756) . SZ) said on the investor interaction platform on April 9 that the first phase of the company's 1 million T / a mining project is a new mine, and it takes about 12 months to reach production from the approval, so the time for the subsequent expansion of the mine to reach production will be shortened